Chemical and Process Engineering |
|||||||||||||||||||||||
|
|||||||||||||||||||||||
|
|
|
|
|
|
||||||||||||||||||
Piping and Instrumentation Diagrams
|
|||||||||||||||||||||||
|
|
|
|
|
|
||||||||||||||||||
Preparation P&IDs,
representing equipment, interconnecting pipe work, instrumentation and
control loops, can be prepared to the level of details required by the
project. P&IDs can include: |
|||||||||||||||||||||||
|
Typical level: |
Conceptual |
Front End |
For Review |
Final |
|
|||||||||||||||||
|
Main
process items |
X |
X |
X |
X |
|
|||||||||||||||||
|
Stream
flags |
X |
X |
X |
X |
|
|||||||||||||||||
|
Main
control loops |
X |
X |
X |
X |
|
|||||||||||||||||
|
Other
control loops |
|
X |
X |
X |
|
|||||||||||||||||
|
Instrumentation |
|
X |
X |
X |
|
|||||||||||||||||
|
Emergency
shut down |
|
X |
X |
X |
|
|||||||||||||||||
|
Sumps
and bunds |
|
X |
X |
X |
|
|||||||||||||||||
|
Relief
devices |
|
X |
X |
X |
|
|||||||||||||||||
|
Strainers
/ Filters |
|
X |
X |
X |
|
|||||||||||||||||
|
Fluid
/ line coding |
|
X |
X |
X |
|
|||||||||||||||||
|
Insulation |
|
X |
+ Tracing |
+ Tracing |
|
|||||||||||||||||
|
Alarms
and trips |
|
|
X |
X |
|
|||||||||||||||||
|
Temporary
strainers |
|
|
X |
X |
|
|||||||||||||||||
|
Piping
vents / drains |
|
|
X |
X |
|
|||||||||||||||||
|
Sampling
points |
|
|
X |
X |
|
|||||||||||||||||
|
Equipment
nozzle ID |
|
|
X |
X |
|
|||||||||||||||||
|
Line
falls / slopes |
|
|
X |
X |
|
|||||||||||||||||
|
Wall/roof
penetrations |
|
|
X |
X |
|
|||||||||||||||||
|
Orifice
plates |
|
|
Not sized |
Sized |
|
|||||||||||||||||
|
Line
sizing and reducers |
|
Preliminary except relief streams |
All except relief streams |
All |
|
|||||||||||||||||
|
|
|
|
|
|
|
|||||||||||||||||
|
Other project specific features may
also be included. |
|
|||||||||||||||||||||
|
|
|
|
|
|
|
|||||||||||||||||
|
|
|
|
|
|
|
|||||||||||||||||
P&ID Checking Checking
of each P&ID includes ensuring that: ·
The
correct drawing format has been used. ·
The
required level of detail has been provided for that issue (eg preliminary, for review, for detailed design, for
construction). ·
Streams
entering or leaving the diagram are accounted for on other diagrams. ·
Tagging
is complete. ·
Equipment
is in agreement with the equipment list and process data sheets. ·
Piping
codes are consistent with the fluid index. ·
Trace
heating and insulation requirements have been met. ·
There
are adequate means of isolation for maintenance of equipment and instruments. |
|||||||||||||||||||||||
|
|
|
|
|
|
|
|||||||||||||||||
Associated Documentation Other
process engineering documents can also be prepared in conjunction with the
P&ID. For example: ·
Instrument
list ·
Alarm
and trip schedule ·
Line
list. ·
Valve
list. ·
Trap
list. ·
Relief
device list. ·
Orifice
list. ·
Process
vents list. ·
Schedule
of special items (eg strainers, flash vessels etc). |
|||||||||||||||||||||||
|
|
|
|
|
|
|
|||||||||||||||||
|
|
|
|
|
|
|
|||||||||||||||||
|
|
|
|
|
|
|
|||||||||||||||||
|
|
|
|
|
|
|
|||||||||||||||||
|
|
|
|||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||||||